India Cuddalore 2×600MW Coal-fired Power Plant Desulfurization EPC Project, undertaken by CDTE in the EPC mode and financed by IL&FS Tamil Nadu Power Company Limited, is the first project in India with EPC Contract directly signed by and between Chinese environmental protection enterprise and the investor, and also the first project undertaken by CDTE by completely adopting the international project management mode. The project site is located at Cuddalore, Tamil Nadu, India, where the tropical climate prevails, with hard working environment and complicated construction conditions. The limestone-gypsum wet desulfurization technology was applied, and booster fan, GGH and 100% fuel gas bypass were provided in the Project, with desulfurization efficiency of 95% (0.8% sulfur content). The Project kicked off on August 25, 2014 and has been put into operation already.