The project, located 1400Km away from Jakarta, is being executed by CGGC as the EPC contractor and supported by preferential buyer’s credit of Chinese government mainly including design, equipment supply, construction and trial operation for 2×100MW Coal-fired Power Plant with the duration of 33 months.